These posts give an overview of the types of projects students in the Arboretum and Public Garden's Learning by Leading™ Waterway Stewardship program lead.

 

Arboretum Waterway Construction Update 3.8.18

The path on the south side of the Arboretum Waterway, which we sometimes refer to as the yellow brick road, is more than halfway complete. Soon the entire walk from the east end of the Arboretum GATEway Garden to the beginning of the Redwood Grove will have a universally accessible path of smooth pavers.

What’s Up, Duck?

We love the ducks in the Arboretum, but too many ducks in the Arboretum Waterway can have negative impacts on the Waterway ecosystem and the ducks.

Waterway edge habitat provides ecosystem benefits

To provide multiple ecosystem benefits, students on our Learning by Leading Waterway Stewardship team are creating riparian (water edge) habitats around the newly constructed weirs throughout Phase One of the Arboretum Waterway Maintenance and Enhancement Project.

Arboretum Waterway Construction Update 1.2.18

The majority of the Arboretum is still open for walking, jogging, strolling, smelling the flowers and all the other activities you normally enjoy in the Arboretum except the portion between our Australian / New Zealand collection at the east end of the Arboretum up to, but not including, the Redwood Grove.

Arboretum Waterway Construction Update 10.26.17

The construction dam is down and water is now back in parts of the phase one project area. (Phase one of the Arboretum Waterway Maintenance and Enhancement Project extends from the easternmost portion of the waterway all the way to Wyatt Deck near Lake Spafford.) We're now working with contractors to test and optimize the pump system, which is an essential part of the waterflow in the Arboretum Waterway.

Arboretum Waterway Construction Update 9.11.17

Four out of the five weirs for Phase 1 of the Arboretum Waterway Maintenance and Enhancement Project are complete, and the last weir should be finished by the end of September. This means we are very close to being able to return water to the channel and watch the water flow over the new weirs and through the wetland plantings.